Hi Saad, here are the milestones. We can discuss further if you like.
Looking forward to start working asap.
I have added number of days after a hyphen and amount after a pipe i.e. | symbol
Suggested milestones - (copy-pasting from milestones section which is not available due to some reason)
Setup ecommerce - 2 | 50
Setup SMTP Email - 0.5 | 30
Install OpenedX system as per edx/configuration repository - 3 | 150
Setup SSL in LMS/CMS - 1 | 40
PayPal integration - 0.5 | 30
SSL in ecommerce - 0.5 | 30
Configure session cookies, create users, remove preview settings - 0.5 | 30
SSL in forum and other services - 1 | 30
Logo, color & copyright customisation - 1 | 50
OpenedX Insights / Analytics pipeline - 2 | 50
Setup certificates - 1 | 50
Edunext WP integration - 1 | 30
WP Job integration - 1 | 30
Jitsi installation and testing on Ubuntu 16.04 - 2 | 100
Course filter and sorting feature - 2 | 20
OpenedX iOS app integration with color and logo customisations - 5 | 150
10-12 XBlocks Bulk Milestone - ora, zoom, recom, grader, audio, anim, rate, school, etc. - 3 | 200
Social login - Google, Facebook and LinkedIn - 2 | 100
BigBlueButton installation - 2 | 150
LTI backend configuration for OpenedX and BBB - 3 | 50